Al-Nasseriya Water Treatment Plant and Transmission Lines
Client: Ministry of Municipalities and Public Works -Water Directorate
Consultant: Poya Tadbir Aria Engineering Company / Axiom Engineering Company
Type of Contract: Turnkey; Engineering, Procurement, Construction (EPC)
Location: Al-Dhi Qar Province, Iraq
Project Overview
Al-Nasseriya water treatment plant and water transmission lines project is located in Dhiqar province, 450 kilometers southeast of Baghdad and 211 kilometers from Basra city.
The water treatment plant of Al-Nasseriya will have a capacity equal to 10,000 cubic meters per hour (equal to 220,000 cubic meters per day), which will be fed from Al-Gharaf river near Al-Nasseriya city. The population covered by this refinery is 1,470,000 people. The treated water of this treatment plant is transported by 118 km long transmission lines to the cities and districts of Al- Nasseriya, Shatra, Sukh al-Sheyukh, and a pumping station is also installed along the route to increase the water pressure.
- Capacity of Al-Nasseriya water treatment plant, Iraq: 10,000 cubic meters per hour (equivalent to 220,000 cubic meters per day)
- The length of transmission lines (diameter 600 to 1400 mm): 118 km
Scope of Work
- Project design in the fields of process, architecture, civil, mechanical, electrical and precision instruments
- Purchase and installation of specialized project equipment
- Carrying out civil and construction operations
- One-year operation and maintenance
Project Statistics
| Length of transmission line | 118 km |
| Logistics and administrative buildings area | 1,950 m² |
| Earth work (pipelines and treatment plants) | 794,000 m³ |
| Concreting | 55,000 m³ |
| Formwork | 146,000 m² |
| Reinforcement | 5,000 t |