Bandar Abbas 200,000 m3 Water Desalination Plant

Bandar Abbas 200,000 m3 Water Desalination Plant

Client: Asia Water Development Engineering Company
MC: Parman Poish Company
Consultant: Pars Geometry Consultanats, Middle East Water and Environment
Type of Contract: PC (Procurement & Construction)
Location: Hormozgan Province, Bandar Abbas
Status: Completed

Project Overview

The project includes:

Execution of water transmission line network to the tie-in points of all treatment plants from the water intake structure

Installation of water intake electromechanical equipment and installation of the relevant pumps

Construction of a 200,000 cubic meter desalination unit in the form of a PC plus 6 months of operation

Execution of the infrastructure network of the treatment plants complex (RO Saqi Kowsar design) with a capacity of one million cubic meters per day

Execution of the fence and site roads

scope of Work

Execution of a 200,000 cubic meter water treatment plant, water transmission line to the treatment plant, and execution of infrastructure facilities for the entire site of Saghi Kowsar project.

General Specifications

Bandar Abbas `200,000 cubic meters water desalination project is one of the modules of the 1,000,000 cubic meters per day desalination project of Asia Water Development Engineering Company, built to use the water produced in the industrial and mining sectors (copper and steel). The result of this project is the production of 200,000 cubic meters of purified water per day in the form of a 200,000 cubic meter desalination plant, which, due to the high TDS of the raw water (from the Persian Gulf), requires a complete pre-treatment along with reverse osmosis technology for water purification.

This project is located on the northern coast of the Persian Gulf, about 35 kilometers west of Bandar Abbas. The meteorological parameters of the project area are as follows:

In the project, except for the water intake and water supply facilities and equipment from the sea to the desalination units, wastewater disposal facilities and infrastructure facilities of the complex, which were executed by the Client, and electricity and raw water within the project area were delivered to the contractor, the rest of the items were entirely the responsibility of the contractor and the construction of a complete set of a 200,000 cubic meter per day desalination unit was the contractor’s commitment.

Project Statistics

Excavation, digging and foundation 330,000 m³
Reinforcement 12,000 t
Concreting 138,000 m³
Heavy steel work 2,000 t
GRP Pipes 27,000 m
Polyethylene pipes 78,000 m
Polyethylene pipes 444 t
Cables 523,000 m
Trans 10 number
Diesels 3 number
Installation of inlet the treatment plant 8 number
Installation of pumps in the pumps of desalination plant 60 number
Installation of all blowers, mixers, compressors inside the desalination water
Installation of all signs MV/LV inside the desalination plant and infrastructure
Installation of all control cables and instrumentation equipment for desalination and infrastructure